Every sourcing calendar for China has one fixed point that does not move: the Spring Festival. In 2027 it falls on 6 February, with the official public holiday running to 12 February. The holiday itself is seven days. The disruption around it is closer to four weeks.
For capsule production this matters more than for most categories. A softgel line cannot idle gracefully. Shell mass, fill temperature, seam quality, drying room humidity all have to be re-stabilised after a cold start, and the crews who hold those parameters steady are the same people travelling home for the holiday.
Brands planning a Q1 launch therefore work backwards from a date in December, not January. The calendar below is the one we use when a customer asks whether a February production slot is realistic.
What Happens on the FloorOutput does not stop on the first day of the holiday. It tapers. Many operators travel well before the official start, so lines run short-staffed through the second half of January. After the holiday, returning workers arrive in waves, and every line needs a restart check before commercial batches resume.
- Late November: filling capacity tightens as brands pull orders forward.
- Early January: last realistic window for bulk production.
- 6 to 12 February: official holiday, site effectively closed.
- Mid to late February: restart, re-qualification, first batch release.
These are the dates we ask brands to hold when a launch depends on a February shipment.
- 15 November: confirm volumes, reserve filling slots, agree the fill weight range.
- 30 November: approve shell material, colour, dosage form, artwork.
- 10 December: release cartons, blisters, labels to production.
- 20 December: sign off the pre-production sample.
- 5 January: last container loading before the slowdown.
Anything approved after 20 December usually lands in March or April, because packaging suppliers close on a similar rhythm and one missing carton stops a finished batch from shipping.
Ocean freight tightens in the same weeks. Carriers add pre-holiday surcharges and space books out early, so a container booked in January often sails in February.
What to Lock, Not Just DiscussA reservation is only as good as the specification behind it. Before the break we ask for the fill weight window in milligrams, the shell type, the colour reference, the blister cavity, the carton dieline, and the market the product is going to. Each item changes either the tooling, the drying profile, or the artwork cycle, and each one reopened in January costs a week.
Stability testing is the quiet constraint. If a formula still needs a three month accelerated read before launch, no amount of production speed recovers that time. Starting stability in November protects a spring shelf date far more than pushing the filling line does.
If the Window Has Already ClosedLate is not the same as lost. Brands sometimes take a first air shipment from stock shell colours on a standard die, then move the balance by sea. Others ship bulk capsules and finish cartons locally. A smaller launch quantity in February is often better than a full launch in April. None of these routes needs new tooling, which is why they can be arranged in weeks rather than months.
Tell us your target market, price positioning, and the launch date you are working toward. We will come back with a formula direction, a fill specification, and a production schedule that reflects the real calendar rather than an optimistic one.